• Home
  • News
  • Daily production record in Kuwait Terminal II Airport

Daily production record in Kuwait Terminal II Airport

Daily production record in Kuwait Terminal II Airport
  • Tuesday, 10 September 2019

Last 26th August, PACADAR achieved a new record in this challenging project, consisting in the manufacture of heavy weight arches, which will hold the roof of the terminal building designed by Foster+Partners. The rough numbers of the project feature a weekly production of 15 pieces -with an average weight of 350Tn-, adding up to 823 pieces and a total precast concrete volume of 69.000m3. Thanks to the hard work and efforts of our team, PACADAR manufactured 6 pieces in a single day, a total weight that exceeds 1.000 tons of concrete and 126 tons of steel reinforcement. PACADAR has set up a precast yard on site with 8 buildings, heavy weight gantries, transport means, and more than 800 people in our staff.

kiat2 2

  • Español (ES)
  • English (UK)