Highway A7 Carchuna-Castel de Ferro viaducts, Spain

Highway A7 Carchuna-Castel de Ferro viaducts, Spain

Manufacture, delivery and assembly of Double-T beams and Decks for three different viaducts at the A7 highway in Spain between Carchuna and Castell del Ferro.

A total of 3 double-T viaducts were executed, having a depth of 2.45 m and beams of up to 46.8 long, with isostatic structure, and weighing up to 100 t.

PACADAR transported and assembled the beams to their final position on the 40 m piers. Our Department of Transport and Assembly carried out the feasibility study needed for obtaining the special transport permit, and also designed the lifting procedure, which required several crawler crane of up to 500 t.

Project Data

  • Client: UTE CARCHUNA CASTELL (FCC-VERA)
  • Owner: Ministry of Public Works and Transport of Spain
  • Year of completion: 2015
  • Contract value: €3,300,000
  • Products provided: double-T beam (HIPERELEFANTE-245-18)
  • Precast volume: 3,300 m³
  • Deck: 20,000 m2

Double T Girders

Quantity Lenght(m) Weight(T) Volume (m3)
6 36 76,32 30,528
61 40 84,80 33,920
52 46 97,52 39,008
8 47 99,64 39,856
    Total m3 4.600,000

Decks

Width (cm) Quantity Strands Area (m2)
65 1504 37/5 5
65 920 17/4 4
65 1078 12/3 3
65 200 21/5 4
    Total m2 15.234